i-80 Gold Announces Positive Preliminary Economic Assessment on the Granite Creek Open Pit Project, Nevada; After-Tax NPV(5%) of $421 Million with an After-Tax IRR of 30% at US$2,175/oz Au

Published on Thu 6 Mar 2025 11:03:01 UTC

This news release constitutes a "designated news release" for the purposes of the Company's prospectus supplement dated August 12, 2024, to its short form base shelf prospectus dated June 21, 2024.

RENO, Nevada, March 6, 2025 /PRNewswire/ - i-80 GOLD CORP. (TSX:IAU) (NYSE:IAUX) ("i-80 Gold", or the "Company")is pleased to announce the results of the preliminary economic assessment (the "PEA") for the Granite Creek Open Pit Project ("Granite Creek Open Pit" or the "Project"). Granite Creek Open Pit is located within the Getchell Trend in northern Nevada, United States, immediately south of the Turquoise Ridge Complex of Nevada Gold Mines.

Figure 6: Granite Creek Open Pit LOM Gold Production Profile vs Cost per Ounce (CNW Group/i-80 Gold Corp)